IMPORTANCE OF UNDERSTANDING ASPHALT INDEX COST INCREASES

 
All paving companies receive a price from the asphalt plants in January of each year. It is hard bidding due to the constant increase in the asphalt and diesel fuel. It is important to understand how to figure the increases when a owner of a project is purchasing a asphalt parking lot. A lot of times we bid work and after a few months the customer will call and say we are ready for the job to start. It is important for all paving contractors to raise costs accordingly. if material increase and the contractor absorbs the increases. The contractor will not be able to operate and will go out of business. Below is a scenario of the increasing costs and how to monitor monthly costs.
 
Example
In January 2006 (Please see chart) Asphalt Index was $ 258.33    
Supplier gives contractors tonnage price.
 
$ 33.50 per ton  January 2006 per ton (I-5 Top cost)
In June 2006 Asphalt Index increases to $ 371.67
 
June Index: $ 371.67
Jan Index:   $ 258.33 (Subtract)
Difference   $ 113.34
 
TAKE $ 113.34 x 5%= $ 5.67 DOLLAR INCREASE ABOVE THE $ 33.50 PRICE GIVEN IN JANUARY 2006
 
Add $ 33.50 + $ 5.67 per ton increase=  $ 39.17 per ton
 
Example: If a project you bid on in January 2006 was taking 1,000 tons of asphalt. The additional cost would be $ 5,670.00. The Asphalt plants will not hold pricing. It can increase at any time. Understand the contractor has no control over increases.!!!!!

 


 

 

 

 

 

Copyright © 2002-2007 Eosso Brothers Paving, Inc.
All rights Reserved.

Web Site Design by U.S. Biz Online